_id: '7783'
abstract:
- lang: eng
  text: The digitization of the industry, the drive towards smart factories as well
    as the Internet of Production (IoP) require rising smartness of products and services.
    Smart physical products are often mechatronic products that include increasing
    amounts of software. The development of software, however, comes along with new
    challenges for companies specialized in developing mechanical, electrical or electronic
    products. Some of these challenges address the product lifecycle management (PLM)-related
    business and work processes. The management of software lifecycles requires a
    much more rigorous requirements management. Furthermore, special solutions for
    management of source code in distributed development teams are needed. The build-process
    and testing activities need to be conducted in a systematic manner. The generation
    and provision of different licensing models need to be mastered and finally the
    issue of security needs to be addressed for any product that can be networked---which
    by the way is a strategic target of nearly any product developing company. Application
    Lifecycle Management (ALM) covers many of the above-mentioned issues. IT solutions
    for ALM are comparable to traditional PLM solutions, but focus particularly on
    software as a product. Thus, these systems have become widely used by software
    companies in the same manner as PLM solutions belong to the standard enterprise
    IT environment of companies developing physical products. With software penetrating
    traditional physical products, product managers, product developers, manufacturing
    staff etc. need to work with both, PLM and ALM, since neither solution is able
    to cover both domains sufficiently. However, ALM and PLM solutions feature redundant
    functionality. Thus, best practices for the systematic integration of ALM and
    PLM are required.
author:
- first_name: Andreas
  full_name: Deuter, Andreas
  id: '62088'
  last_name: Deuter
  orcid: 0000-0002-6529-6215
- first_name: Andreas
  full_name: Otte, Andreas
  id: '51466'
  last_name: Otte
- first_name: Marcel
  full_name: Ebert, Marcel
  last_name: Ebert
- first_name: Frank
  full_name: Possel-Dölken, Frank
  last_name: Possel-Dölken
citation:
  ama: 'Deuter A, Otte A, Ebert M, Possel-Dölken F. Developing the Requirements of
    a PLM/ALM Integration: An Industrial Case Study. In: Stark J, ed. <i>Product Lifecycle
    Management (Volume 4)</i>. Decision Engineering. Springer; 2019:125-143. doi:<a
    href="https://doi.org/10.1007/978-3-030-16134-7_11">10.1007/978-3-030-16134-7_11</a>'
  apa: 'Deuter, A., Otte, A., Ebert, M., &#38; Possel-Dölken, F. (2019). Developing
    the Requirements of a PLM/ALM Integration: An Industrial Case Study. In J. Stark
    (Ed.), <i>Product lifecycle management (Volume 4)</i> (pp. 125–143). Springer.
    <a href="https://doi.org/10.1007/978-3-030-16134-7_11">https://doi.org/10.1007/978-3-030-16134-7_11</a>'
  bjps: '<b>Deuter A <i>et al.</i></b> (2019) Developing the Requirements of a PLM/ALM
    Integration: An Industrial Case Study. In Stark J (ed.), <i>Product Lifecycle
    Management (Volume 4)</i>. Cham, Switzerland: Springer, pp. 125–143.'
  chicago: 'Deuter, Andreas, Andreas Otte, Marcel Ebert, and Frank Possel-Dölken.
    “Developing the Requirements of a PLM/ALM Integration: An Industrial Case Study.”
    In <i>Product Lifecycle Management (Volume 4)</i>, edited by John Stark, 125–43.
    Decision Engineering. Cham, Switzerland: Springer, 2019. <a href="https://doi.org/10.1007/978-3-030-16134-7_11">https://doi.org/10.1007/978-3-030-16134-7_11</a>.'
  chicago-de: 'Deuter, Andreas, Andreas Otte, Marcel Ebert und Frank Possel-Dölken.
    2019. Developing the Requirements of a PLM/ALM Integration: An Industrial Case
    Study. In: <i>Product lifecycle management (Volume 4)</i>, hg. von John Stark,
    125–143. Decision Engineering. Cham, Switzerland: Springer. doi:<a href="https://doi.org/10.1007/978-3-030-16134-7_11">10.1007/978-3-030-16134-7_11</a>,
    .'
  din1505-2-1: '<span style="font-variant:small-caps;">Deuter, Andreas</span> ; <span
    style="font-variant:small-caps;">Otte, Andreas</span> ; <span style="font-variant:small-caps;">Ebert,
    Marcel</span> ; <span style="font-variant:small-caps;">Possel-Dölken, Frank</span>:
    Developing the Requirements of a PLM/ALM Integration: An Industrial Case Study.
    In: <span style="font-variant:small-caps;">Stark, J.</span> (Hrsg.): <i>Product
    lifecycle management (Volume 4)</i>, <i>Decision Engineering</i>. Cham, Switzerland :
    Springer, 2019, S. 125–143'
  havard: 'A. Deuter, A. Otte, M. Ebert, F. Possel-Dölken, Developing the Requirements
    of a PLM/ALM Integration: An Industrial Case Study, in: J. Stark (Ed.), Product
    Lifecycle Management (Volume 4), Springer, Cham, Switzerland, 2019: pp. 125–143.'
  ieee: 'A. Deuter, A. Otte, M. Ebert, and F. Possel-Dölken, “Developing the Requirements
    of a PLM/ALM Integration: An Industrial Case Study,” in <i>Product lifecycle management
    (Volume 4)</i>, J. Stark, Ed. Cham, Switzerland: Springer, 2019, pp. 125–143.
    doi: <a href="https://doi.org/10.1007/978-3-030-16134-7_11">10.1007/978-3-030-16134-7_11</a>.'
  mla: 'Deuter, Andreas, et al. “Developing the Requirements of a PLM/ALM Integration:
    An Industrial Case Study.” <i>Product Lifecycle Management (Volume 4)</i>, edited
    by John Stark, Springer, 2019, pp. 125–43, <a href="https://doi.org/10.1007/978-3-030-16134-7_11">https://doi.org/10.1007/978-3-030-16134-7_11</a>.'
  short: 'A. Deuter, A. Otte, M. Ebert, F. Possel-Dölken, in: J. Stark (Ed.), Product
    Lifecycle Management (Volume 4), Springer, Cham, Switzerland, 2019, pp. 125–143.'
  ufg: '<b>Deuter, Andreas u. a.</b>: Developing the Requirements of a PLM/ALM Integration:
    An Industrial Case Study, in: <i>Stark, John (Hg.)</i>: Product lifecycle management
    (Volume 4), Cham, Switzerland 2019 (Decision Engineering),  S. 125–143.'
  van: 'Deuter A, Otte A, Ebert M, Possel-Dölken F. Developing the Requirements of
    a PLM/ALM Integration: An Industrial Case Study. In: Stark J, editor. Product
    lifecycle management (Volume 4). Cham, Switzerland: Springer; 2019. p. 125–43.
    (Decision Engineering).'
date_created: 2022-04-25T10:46:14Z
date_updated: 2025-06-26T13:40:03Z
department:
- _id: DEP7022
- _id: DEP1306
doi: 10.1007/978-3-030-16134-7_11
editor:
- first_name: John
  full_name: Stark, John
  last_name: Stark
keyword:
- Product lifecycle management
- Application Lifecycle Management
- Smart products
- Systems engineering
language:
- iso: eng
page: 125-143
place: Cham, Switzerland
publication: Product lifecycle management (Volume 4)
publication_identifier:
  eisbn:
  - 978-3-030-16134-7
  eissn:
  - 2197-6589
  isbn:
  - 978-3-030-16133-0
  issn:
  - 1619-5736
publication_status: published
publisher: Springer
series_title: Decision Engineering
status: public
title: 'Developing the Requirements of a PLM/ALM Integration: An Industrial Case Study'
type: book_chapter
user_id: '83781'
year: '2019'
...
---
_id: '12798'
abstract:
- lang: eng
  text: "The digitization of the industry requires smart products and services. Smart
    products are mechatronic products with an increasing amount of software. To get
    high quality smart products to the market quickly, manufacturers need to reshape
    their product lifecycle processes. They need to apply system engineering-based
    methods to enable smooth cross-domain developments with a special focus on the
    software domain. One significant challenge faced by manufacturers is the harmonization
    of product lifecycle management (PLM), which addresses the hardware lifecycle,
    with application lifecycle management (ALM), which addresses the software lifecycle.\r\n\r\nTo
    support manufacturers in this challenging activity, this paper demonstrates a
    proven process for developing use cases and requirements associated with a PLM/ALM
    integration. This process has been elicited during an industrial case study in
    a manufacturing company. This paper explains this process in detail. A generally
    applicable approach for developing the requirements of a PLM/ALM integration is
    extracted by removing the company-specific factors. "
author:
- first_name: Andreas
  full_name: Deuter, Andreas
  id: '62088'
  last_name: Deuter
  orcid: 0000-0002-6529-6215
- first_name: Andreas
  full_name: Otte, Andreas
  id: '51466'
  last_name: Otte
- first_name: Marcel
  full_name: Ebert, Marcel
  last_name: Ebert
- first_name: Frank
  full_name: Possel-Dölken, Frank
  last_name: Possel-Dölken
citation:
  ama: 'Deuter A, Otte A, Ebert M, Possel-Dölken F. <i>Developing the Requirements
    of a PLM/ALM Integration: An Industrial Case Study</i>. Vol 24. (Denkena B, Thoben
    KD, Trachtler A, eds.). Elsevier BV; 2018:107-113. doi:<a href="https://doi.org/10.1016/j.promfg.2018.06.020">10.1016/j.promfg.2018.06.020</a>'
  apa: 'Deuter, A., Otte, A., Ebert, M., &#38; Possel-Dölken, F. (2018). Developing
    the Requirements of a PLM/ALM Integration: An Industrial Case Study. In B. Denkena,
    K. D. Thoben, &#38; A. Trachtler (Eds.), <i>4th International Conference on System-Integrated
    Intelligence - Intelligent, Flexible and Connected Systems in Products and Production</i>
    (Vol. 24, pp. 107–113). Elsevier BV. <a href="https://doi.org/10.1016/j.promfg.2018.06.020">https://doi.org/10.1016/j.promfg.2018.06.020</a>'
  bjps: '<b>Deuter A <i>et al.</i></b> (2018) <i>Developing the Requirements of a
    PLM/ALM Integration: An Industrial Case Study</i>, Denkena B, Thoben KD and Trachtler
    A (eds). Amsterdam [u.a.]: Elsevier BV.'
  chicago: 'Deuter, Andreas, Andreas Otte, Marcel Ebert, and Frank Possel-Dölken.
    <i>Developing the Requirements of a PLM/ALM Integration: An Industrial Case Study</i>.
    Edited by B. Denkena, K. D.  Thoben, and A. Trachtler. <i>4th International Conference
    on System-Integrated Intelligence - Intelligent, Flexible and Connected Systems
    in Products and Production</i>. Vol. 24. Procedia Manufacturing. Amsterdam [u.a.]:
    Elsevier BV, 2018. <a href="https://doi.org/10.1016/j.promfg.2018.06.020">https://doi.org/10.1016/j.promfg.2018.06.020</a>.'
  chicago-de: 'Deuter, Andreas, Andreas Otte, Marcel Ebert und Frank Possel-Dölken.
    2018. <i>Developing the Requirements of a PLM/ALM Integration: An Industrial Case
    Study</i>. Hg. von B. Denkena, K. D.  Thoben, und A. Trachtler. <i>4th International
    Conference on System-Integrated Intelligence - Intelligent, Flexible and Connected
    Systems in Products and Production</i>. Bd. 24. Procedia Manufacturing. Amsterdam
    [u.a.]: Elsevier BV. doi:<a href="https://doi.org/10.1016/j.promfg.2018.06.020">10.1016/j.promfg.2018.06.020</a>,
    .'
  din1505-2-1: '<span style="font-variant:small-caps;">Deuter, Andreas</span> ; <span
    style="font-variant:small-caps;">Otte, Andreas</span> ; <span style="font-variant:small-caps;">Ebert,
    Marcel</span> ; <span style="font-variant:small-caps;">Possel-Dölken, Frank</span>
    ; <span style="font-variant:small-caps;">Denkena, B.</span> ; <span style="font-variant:small-caps;">Thoben,
    K. D.</span> ; <span style="font-variant:small-caps;">Trachtler, A.</span> (Hrsg.):
    <i>Developing the Requirements of a PLM/ALM Integration: An Industrial Case Study</i>,
    <i>Procedia Manufacturing</i>. Bd. 24. Amsterdam [u.a.] : Elsevier BV, 2018'
  havard: 'A. Deuter, A. Otte, M. Ebert, F. Possel-Dölken, Developing the Requirements
    of a PLM/ALM Integration: An Industrial Case Study, Elsevier BV, Amsterdam [u.a.],
    2018.'
  ieee: 'A. Deuter, A. Otte, M. Ebert, and F. Possel-Dölken, <i>Developing the Requirements
    of a PLM/ALM Integration: An Industrial Case Study</i>, vol. 24. Amsterdam [u.a.]:
    Elsevier BV, 2018, pp. 107–113. doi: <a href="https://doi.org/10.1016/j.promfg.2018.06.020">10.1016/j.promfg.2018.06.020</a>.'
  mla: 'Deuter, Andreas, et al. “Developing the Requirements of a PLM/ALM Integration:
    An Industrial Case Study.” <i>4th International Conference on System-Integrated
    Intelligence - Intelligent, Flexible and Connected Systems in Products and Production</i>,
    edited by B. Denkena et al., vol. 24, Elsevier BV, 2018, pp. 107–13, <a href="https://doi.org/10.1016/j.promfg.2018.06.020">https://doi.org/10.1016/j.promfg.2018.06.020</a>.'
  short: 'A. Deuter, A. Otte, M. Ebert, F. Possel-Dölken, Developing the Requirements
    of a PLM/ALM Integration: An Industrial Case Study, Elsevier BV, Amsterdam [u.a.],
    2018.'
  ufg: '<b>Deuter, Andreas u. a.</b>: Developing the Requirements of a PLM/ALM Integration:
    An Industrial Case Study, Bd. 24, hg. von Denkena, B./Thoben, K.D./Trachtler,
    A., Amsterdam [u.a.] 2018 (Procedia Manufacturing).'
  van: 'Deuter A, Otte A, Ebert M, Possel-Dölken F. Developing the Requirements of
    a PLM/ALM Integration: An Industrial Case Study. Denkena B, Thoben KD, Trachtler
    A, editors. 4th International Conference on System-Integrated Intelligence - Intelligent,
    Flexible and Connected Systems in Products and Production. Amsterdam [u.a.]: Elsevier
    BV; 2018. (Procedia Manufacturing; vol. 24).'
conference:
  end_date: 20218-06-20
  location: Hannover
  name: 4th International Conference on System-Integrated Intelligence - Intelligent,
    Flexible and Connected Systems in Products and Production
  start_date: 2018-06-19
date_created: 2025-04-15T12:50:25Z
date_updated: 2025-06-26T13:39:42Z
department:
- _id: DEP7022
- _id: DEP1306
doi: 10.1016/j.promfg.2018.06.020
editor:
- first_name: B.
  full_name: Denkena, B.
  last_name: Denkena
- first_name: 'K. D. '
  full_name: 'Thoben, K. D. '
  last_name: Thoben
- first_name: A.
  full_name: Trachtler, A.
  last_name: Trachtler
intvolume: '        24'
keyword:
- Product lifecycle management
- Application Lifecycle Management
- Smart products
- Systems engineering
language:
- iso: eng
page: 107-113
place: Amsterdam [u.a.]
publication: 4th International Conference on System-Integrated Intelligence - Intelligent,
  Flexible and Connected Systems in Products and Production
publication_identifier:
  issn:
  - 2351-9789
publication_status: published
publisher: Elsevier BV
series_title: Procedia Manufacturing
status: public
title: 'Developing the Requirements of a PLM/ALM Integration: An Industrial Case Study'
type: conference_editor_article
user_id: '83781'
volume: 24
year: '2018'
...